Metro Vancouver Golden Ears Forcemain and River Crossing Project



Date Posted : November 30, 2020

in : Projects


In November 2020, a project permit was issued to Metro Vancouver to design, construct, and install twin sewer forcemains beneath the Fraser River to connect the new Golden Ears Pump Station, located north of the Fraser River, to the expanded Northwest Langley Wastewater Treatment Plant. The project area is on federal waters managed by the Vancouver Fraser Port Authority.


Ground X will be removing 130,000 Tonnes over 3 years

The project was approved subject to 27 permit conditions that Metro Vancouver must meet to ensure the project does not result in significant adverse environmental effects. The anticipated construction timeline is from July 2021 to March 2022.


    Link

    For more information, please visit this website.